Large Residential Community
PARKING LOT
MATTHEWS, NC
ISSUE
Large community requested a new 218 space parking lot for staff which required extension of a roadway, utilities, and sidewalk. The parking lot and roadway extension were in areas of poor subgrade soils and shallow groundwater.
SOLUTION
-
Clearing and preparation of over 5 acres
-
Installation and maintenance of all erosion control including inspection services.
-
Export of over 40,000 yd³ of unsuitable materials.
-
400 tons of Portland subgrade stabilization.
-
Import of over 15,000 tons of aggregates for subgrade preparation.
-
Nearly 1,000 LF of new stormwater pipelines and associated structures.
-
500 LF of new waterline with valves and hydrant.
-
Installation of over 1,800 LF of new curb
-
Installation of over 1,600 LF of new sidewalk.
-
Over 8,000 yd² of asphalt paving including striping and signs.
-
New LED street lighting package.
RESULTS
The project required multiple trades and very tight logistics. It was successful considering completion 2-weeks ahead of our deadline.