COLLISON CENTER
STORMWATER CLEANOUT
CONCORD, NC
ISSUE
Existing commercial property with a large underground stormwater detention and filtration system requiring a full cleanout, multiple repairs, and filtration servicing.
SOLUTION
-
Confined space entry along with atmospheric controls.
-
Cleanout of over 1,200 LF of 96” pipeline and several junction and overflow structures.
-
The removal and replacement of 26 Contech perlite filter cartridges along with replacement of cast floor mounts.
-
Transportation and disposal of over 40,000 gallons of waste sludge.
RESULTS
The project required multiple personnel and extensive logistics while maintaining operation of the on-site business.
The project was a success as the detention system flows and filters as designed.